New Tile, Countertops, & Paint

August 12th, 2008 by Ryan

We are in the final stretch and have an estimated 3 weeks to completion. The wood floors are in and just need to be stained. The tile is finished in the kitchen and both bathrooms as well. The kitchen should be entirely done by Wednesday (8/13). There is one more day of painting which we will do this coming Saturday. There are a few 2nd coats left and all the master bedroom/bathroom still needs to be painted. Brandon and Bob have started the deck and the ceiling of the master bedroom, which will be tongue and groove wood.

Posted in Uncategorized


Interior stuff

July 21st, 2008 by Brandon

Since the last post the interior of our house has come along way.  The kitchen tile is almost done, the cabinets have been installed and the walls are painted.  The rest of the house is drywalled, floated and textured.  We will probably do a lot of the painting this coming weekend.  The interior doors arrived however half of them were wrong so we’ll have all of them by the end of this week. 

In the next two or two we will get the floor installed.  The wood, white oak, comes unfinshed which mean that first you nail it down.  Then you have to sand and stain it.  We are going to begin the nailing down part starting next week.  The tile is also being ordered and will start going in next week. 

After all the floor is installed we can begin the final phase.  This includes mounting all the vanities, triming out the windows and doors, doing the plumbing top out, electric trim and mechanical final. 

 

 

Posted in Uncategorized


Just the interior now… well and a deck

July 1st, 2008 by Brandon

So as many of you know I’m not very computer compatiable thus posting is a bit of a process for me.  What’s happened in the past three weeks?  Well, the first round of inspections have all passed (on the first try I might add).  This means that the frame is complete, all the electrical wire have been pulled, the AC/heating is installed just not on yet, and all the pipes for our plumbing system are in and water tight.  All in all we are moving along quite nicely. 

 

The next few weeks will include insulating the walls, hanging, taping floating and texturing the drywall, installing our backyard deck, then painting the walls.  So alot of wall work basically.  After that we can start triming the house and installing the interior doors. 

 

 

Posted in Uncategorized


New Roof & Paint

July 1st, 2008 by Ryan

There is new paint on the house with the trim still yet to be done. Roofers were there yesterday putting on shingles. There is one last inspection that we must pass before we can do insulation and drywall on the inside. Sorry about the lull in posts, but hopefully you’ve been able to follow our progress by the photos.

Ginny added a new PLANS tab on the top that shows the old and new floorplans, which were done by Nicole Durkin. I will have Brandon post about the past few weeks since he will be able to give more insight. Once the Tyvek and siding went up, it’s been smaller and more behind the scenes work at 1903.

Posted in Uncategorized


It’s all coming together

June 7th, 2008 by Ryan

The plumbing is in and all the framing is complete. The windows and doors were delivered on Thursday from Marvin Windows. Brandon and Bob put in new 2 x 8’s in the ceiling over the living room since the load bearing supports below that were removed. This is where the kitchen table used to be (see Gallery from March 25 and May 13). I believe the electrician will be by early next week to do his thing.

Posted in Uncategorized