Interior stuff
July 21st, 2008 by BrandonSince the last post the interior of our house has come along way. The kitchen tile is almost done, the cabinets have been installed and the walls are painted. The rest of the house is drywalled, floated and textured. We will probably do a lot of the painting this coming weekend. The interior doors arrived however half of them were wrong so we’ll have all of them by the end of this week.
In the next two or two we will get the floor installed. The wood, white oak, comes unfinshed which mean that first you nail it down. Then you have to sand and stain it. We are going to begin the nailing down part starting next week. The tile is also being ordered and will start going in next week.
After all the floor is installed we can begin the final phase. This includes mounting all the vanities, triming out the windows and doors, doing the plumbing top out, electric trim and mechanical final.